Nordic/PCL, a Hawaiian Joint Venture
Current Progress

Update 1/17/08

In the last 2 weeks:

  • Pool slide installation is 100% complete.
  • Form, reinforce and pour slide encasement is 100% complete.
  • Installation of piping at upper pool is 75% complete.
  • Forming of upper pool bondbeam is 100% complete.
  • Form, reinforce, and pour pool bar deck is 100% complete.
  • Elevator installation is 30% complete.
  • Phase 4 fireproofing is 85% complete.
  • Phase 4 EIFS is 75% complete to level 12.
  • Contract completion punchlist is 95% complete for level 7.
  • Contract completion punchlist is 95% complete for level 8.
  • Contract completion punchlist is 75% complete for level 9.
  • Contract completion punchlist is 50% complete for level 10
  • Level 10, plumbing fixtures and trim is 100% complete.
  • Level 10, electrical fixtures and trim is 100% complete.
  • Level 10, appliance installation is 100% complete.
  • Level 11, wall and floor ceramic tile is 75% complete.
  • Level 11, plumbing and electrical fixtures and trim is 100% complete.
  • Level 11, resilient flooring is 95% complete.
  • Level 12, cabinet installation is 100% complete.
  • Level 12, door and millwork installation is 100% complete.
  • Level 12, granite slabs are 95% complete.
  • Level 12, wall and floor tile is 75% complete.
  • Level 14, shower pans and mortar beds are 100% complete.
  • Level 14, cabinet installation is 75% complete.
  • Level 14, door and millwork installation is 85% complete.
  • Level 15, GWB tape and texture is 100% complete.
  • Level 15, paint primer and first coat is 100% complete.
  • Level 15, granite slabs are 50% complete.
  • Level 16, ceiling framing is 25% complete.
  • Level 16, MEP rough in is 100% complete.
  • Level 16, GWB hanging is 25% complete.


In the next 2 weeks:

  • Pool piping and utilities will be 100% complete.
  • Rockwork at lower pool will be 25% complete.
  • Stairs to water slide will be 100% complete.
  • Retaining rock work at slide stairs will be 100% complete.
  • Upper pool gunnite will be 100% complete.
  • Coconut tree installation at pool bar will be 10% complete.
  • Elevator installation will be 40% complete.
  • Elevator entrance installation will be 100% complete.
  • Phase 4 EIFS will be 75% complete to level 14.
  • Exterior stone cladding will be 25% complete.
  • Traffic coating at pool pump rooms will be 100% complete.
  • Gutter installation at stair 3, 3A, 3B roofs will be 100% complete.
  • Copper roofing at stair 3, 3A, and 3B roofs will be 50% complete.
  • Contract completion punchlist will be 100% complete for level 3.
  • Contract completion punchlist will be 100% complete for level 4.
  • Contract completion punchlist will be 50% complete for level 5.
  • Level 14, wall and floor tile will be 100% complete.
  • Level 14, shower pans and mortar beds will be 100% complete.
  • Level 14, cabinet installation will be 100% complete.
  • Level 14, door and millwork installation will be 100% complete.
  • Level 15, cabinet installation will be 100% complete.
  • Level 15, granite slab installation will be 100% complete.
  • Level 15, wall and floor tile installation will be 50% complete.
  • Level 16, prime and first coat of paint will be 100% complete.
  • Level 16, shower pans and mortar beds will be 100% complete.
  • Level 16, cabinet installation will be 75% complete.
  • Level 16, door and millwork installation will be 60% complete.
Project Description

The Marriott Vacation Club Inc. (MVCI) Beachclub Phase 4-5 is the construction of shell space for 246 timeshare units including full build-out of 114 timeshare units.  The project is located in the Ko Olina resort on the Western end of Oahu approximately 20 miles from Honolulu, Hawaii.  The original contract includes Phase 4 with Phase 5 as an alternate to be added at a later date. 

The total project is 643,150 square feet with the building enclosing approximately 489,379 square feet of timeshare unit and shell space.  This building is connected to a 367 stall above and below grade parking structure with 61 stalls of surface parking, all located on a 5.3 acre site. The foundation system is a blend of drilled shafts and pile caps with strip footings. All buildings are cast-in-place concrete structures with post tensioned elevated decks.  The exterior wall system is EFIS on metal studs with a limited amount of stone facing in two entry areas.  The roofing system is primarily sloping metal roofing with a small amount of flat membrane roofing.  Each unit is cooled by vertical fan coil units which are fed from a central plant.  The Owner is furnishing the carpet, pad, and decorative light fixtures.

Phase 4 is comprised of the construction of 14 levels above grade and 2 levels below grade of building structure, shell space, parking structure and a portion of the landscaping improvements.  This phase includes the complete build-out of 114 luxury timeshare units.  The structured parking is comprised of two levels below the timeshare tower and 6 each ½ levels outside of the tower footprint.  The high-end finishes include granite countertops, ceramic tile bathrooms, beautiful wood doors, and plenty of millwork.  The site work includes extensive tropical themed pools with a water slide. 

Phase 5 is an alternate in Phase 4 base building contract.  This phase of work is for the tenant improvement construction of the remaining 132 timeshare units in the Phase 4 shell.  The finishes for these units will be the same as those in Phase 4.  The Owner anticipates issuing a change order for this work during the construction of Phase 4.  The actual notice to proceed date for this work will depend on timeshare unit sales.

The overall schedule will vary depending on the notice to proceed date for Phase 5.  The base building Phase 4 contract is for 26 months.

 

 